RCTC – 15 Express Lanes Construction Gallery – April 7, 2020
Click the thumbnails to view a larger image of the work completed through April 7, 2020.
Click the thumbnails to view a larger image of the work completed through April 7, 2020.
Click the thumbnails to view a larger image of the work completed through March 3, 2020.
Click the thumbnails to view a larger image of the work completed through January 24, 2020.
Click the thumbnails to view a larger image of the work completed through December 13, 2019.
A major milestone on the 15 Express Lanes project was achieved. The last of the 55 precast girders used to widen the Santa Ana River Bridge was installed mid-November 2019. Weighing in at 132 tons each and the size of a blue whale, these girders were transported at night over the past several months. Crews […]
Click the thumbnails to view a larger image of the Nightwork completed on June 25, 2018.
Click the thumbnails to view a larger image.
Alternating nighttime lane closures are scheduled next week on northbound and southbound I-15 between State Route 60 and the Santa Ana River. The lane closures are needed for shoulder paving, striping, sawcutting and installing k-rail. At least one lane will remain open during alternating lane closures. The outside lane (the lane closest to the shoulder) also […]
Alternating lane closures are scheduled nightly on northbound and southbound I-15 from Sunday, April 15 to Friday, April 20. At least two lanes in each direction will remain open at all times. Northbound lane closures will take place nightly from 8 p.m. to 5 a.m. between the Santa Ana River and Bellegrave Avenue. Southbound lane […]
Alternating lane closures are scheduled at night on northbound and southbound I-15 between SR-60 and the Santa Ana River. At least two lanes will remain open at all times. Crews will be paving the freeway shoulders as part of shoulder strengthening work to allow traffic shifts during construction. The scheduled lane closures are: Pictured below: […]
View images of Sound Wall S1-A I-15 Southbound between El Cerrito Road and Cajalco Road. Crews will begin working extended shifts until 10:30 pm this week to expedite sound wall construction. Formwork on sound wall S1-A will be removed once the concrete has cured. Click the thumbnails to view a larger image.
Nighttime lane closures are scheduled next week on I-15 for crews to grind the median shoulder pavement. The two left lanes closest to the median are expected to close the following nights: Crews are scheduled to work on the southbound I-15 soundwall between El Cerrito Road and Cajalco Road from Monday, April 2 to Saturday, […]