NIGHTTIME RAMP CLOSURES ON I-15

Intermittent lane reductions are scheduled on northbound and southbound 15, between Weirick Rd. and State Route 60, from 8 p.m. to 5 a.m., weeknights. During lane reductions, at least one lane will remain open at all times.

Closures on northbound and southbound express lane connectors are also planned intermittently on weeknights from 10 p.m. to 4 a.m. Detours will be clearly marked.

The closure schedule is as follows:

Date, Time Location Detour
Monday, Sept. 9
9 p.m. to 5 a.m.
Northbound 15
Magnolia Ave. on-rampEastbound 91 to Northbound 15 Connector
Use Ontario Ave.

Use Magnolia Ave.

Thursday, Sept. 12
10 p.m. to 5 a.m.
Eastbound 91 to Northbound 15 Connector

Eastbound 91 to Southbound 15 Connector

Use McKinley St.
 
Friday, Sept. 13
9 p.m. to 4 a.m.
Northbound 15
Hidden Valley Pkwy. on- and off-rampSouthbound 15
Magnolia Ave. on-rampWestbound 91 to Northbound 15 Connector

Eastbound 91 to Northbound 15 Connector

Use Second St. or Parkridge Ave.

Use Ontario Ave.

Use Magnolia Ave.

 


15 PROJECT GIRDERS ARE “ON THE GO”

Have you seen the heaviest concrete girders ever made in California? These 132-ton girders are traveling at night by truck over the next several months from Perris to the Santa Ana River Bridge in Norco as part of the 15 Express Lanes project.

Crews are widening the massive Santa Ana River Bridge using 55 girders. The girder transport will occur intermittently on weeknights during off-peak hours, beginning at 1 a.m. Motorists can expect short traffic breaks and lane closures over the next few months until all 55 girders complete their journey to the project site.

 


Neighboring Projects

60 Swarm Pavement Rehabilitation Project: Full closures of eastbound State Route 60, between I-15 and the 60/91/215 interchange in Riverside, are continuing. For more information, visit www.60swarm.com.

Cajalco Rd. / I-15 Interchange Improvement Project: For schedule and closure information, visit i15cajalco.com for closure information.

Limonite Ave / I-15 Interchange Improvement Project: For schedule and closure information, visit i15limonite.org .

 


Due to the dynamic nature of construction, this information is subject to change.

If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.

Print Friendly, PDF & Email