Construction Update – Week of Sept 7

In observance of Labor Day, no closures are scheduled from Friday, Sept. 4 through Monday, Sept. 7. Please drive safely and enjoy the holiday weekend!

 

 


LANE, RAMP & CONNECTOR CLOSURES

Nighttime lane reductions (8 p.m. to 5 a.m.) may be needed on northbound and southbound I-15, between Weirick Rd. and Route 60, and on westbound and eastbound 91, between McKinley St. and Main St. During lane reductions, at least one lane will remain open at all times.

Intermittent nighttime closures on ramps, the 15/91 connectors and 15/60 connectors are also planned.

The closure schedule is as follows:

Date, Time Location
Monday, September 7

 

No closures in observance
 of  Labor Day 
Tuesday, September  8

8 p.m. to 5 a.m.

15 Northbound
Magnolia on-ramp
Wednesday, September 9

8 p.m. to 5 a.m.

15 Northbound
Ontario Ave. off-ramp
El Cerrito Rd. on-ramp
Limonite Ave. on- & off-ramps

15 Southbound
Magnolia Ave. off-ramp

Thursday, September 10

8 p.m. to 5 a.m.

 

15 Northbound
Magnolia Ave. on-ramp
Hidden Valley Pkwy. on-ramp
Friday, September 11

9 p.m. to 5 a.m.

 

 

15 Southbound
Magnolia Ave. on- & off-ramps
Hidden Vallley Pkwy. on-ramp

91 EXPRESS LANES NIGHTTIME CLOSURES  

Nightly closures are scheduled of the 91 Express Lanes and adjacent general purpose lane between the 55/91 Interchange and the Orange/Riverside County line. The closure schedule is as follows:

  • 91 Express Lanes westbound and adjacent 91 westbound general-purpose lane, September 8-11, nightly from 8 p.m. to 4 a.m.
  • 91 Express Lanes eastbound and adjacent 91 eastbound general-purpose lane, September 8-11, nightly from 9 p.m. to 5 a.m.

91 EXPRESS LANES SOUTHBOUND CONNECTOR EXTENDED FOR TOLL CUSTOMERS  

As construction continues on the 15 Express Lanes, motorists may have noticed changes while driving in the project area.

The 91 Express Lanes to southbound 15 was extended 1.5 miles to allow customers to continue in the Express Lanes until Cajalco Road at no extra charge. This extension is an early benefit to southbound 91 Express Lanes customers and helps improve traffic flow in the area.  Watch for new signs to note this temporary condition.

Please remember to drive safely in the project area, as crews remain at work until the 15 Express Lanes open, which is expected in late 2020.     


TOLL EQUIPMENT TESTING CONTINUES ON 15 EXPRESS LANES 

Crews continue testing toll equipment along Interstate 15 to prepare for the future opening of the 15 Express Lanes. During testing, vehicles will be traveling in the closed median of the 15 Express Lanes.


Due to the dynamic nature of construction, this information is subject to change.