Construction Update – Week of Oct 7

FULL NIGHTTIME CLOSURE ON I-15

A complete closure of the northbound 15 from Magnolia Ave. to the 91 is scheduled Monday night, Oct. 7 from 10 p.m. to 4 a.m. for overhead sign removal.

The northbound Magnolia Ave. on-ramp and eastbound 91 to southbound 15 express lane connector also will be closed.

DETOUR: Motorists should use the 91 or McKinley St. as a detour.


I-15 RAMP & LANE CLOSURES

Intermittent lane reductions are scheduled on northbound and southbound 15, between Weirick Rd. and State Route 60, weeknights. During lane reductions, at least one lane will remain open at all times.

The closure schedule is as follows:

Date, Time Location Detour
Monday, Oct. 7
8 p.m. to 4 a.m.
Magnolia Ave.
Northbound 15 on-ramp
Use McKinley St.
Tuesday, Oct. 8
8 p.m. to 5 a.m.
Hidden Valley Pkwy.
Northbound &
Southbound 15
on- and off-ramps
Use Second St.
Wednesday, Oct. 9
8 p.m. to 5 a.m.
Hidden Valley Pkwy.
Northbound 15
on- and off-rampsMagnolia Ave.
Northbound 15 on-ramp
Use Second St.

Use Ontario Ave.

Thursday, Oct. 10
8 p.m. to 5 a.m.
Second St.
Northbound 15 on-rampHidden Valley Pkwy.
Northbound 15 off-ramp
Use Sixth St.

Use Second St.

 


CONNECTOR CLOSURES

Closures of the 15/91 connectors are also planned weeknights. Detours will be clearly marked.

The closure schedule is as follows:

Date, Time Location Detour
Monday, Oct. 7
9 p.m. to 5 a.m.
Eastbound 91 to southbound 15 connector Use McKinley St.
Tuesday, Oct. 8
9 p.m. to 6 a.m.
Westbound 91 to southbound & northbound 15 connectors

Eastbound 91 to southbound 15 connector

Use Main St.
Wednesday, Oct. 9
9 p.m. to 5 a.m.
Westbound 91 to northbound 15 connector Use Main. St.
Thursday, Oct. 10 &
Friday, Oct. 11
8 p.m. to 5 a.m.
Southbound 15 to westbound 91 connector Use Magnolia Ave.

55 MPH IN CONSTRUCTION ZONE

Please drive slowly and carefully in the 15 Express Lanes construction project area for your safety and the safety of our construction workers. The speed limit is 55 miles per hour for the full project limits. Traffic fines are doubled in a construction zone.


VIDEO: CONSTRUCTION RECAP

See what crews accomplished last month on the 15 Express Lanes project in our latest construction recap video.


Neighboring Projects

60 Swarm Pavement Rehabilitation Project: : : Full closures of westbound State Route 60, between I-15 and the 60/91/215 interchange in Riverside, will occur through November. For more information, visit www.60swarm.com.

Cajalco Rd. / I-15 Interchange Improvement Project: For schedule and closure information, visit i15cajalco.com .

Limonite Ave / I-15 Interchange Improvement Project: For schedule and closure information, visit i15limonite.org .


Due to the dynamic nature of construction, this information is subject to change.