Construction Update – Week of Oct 28

I-15 RAMP & LANE CLOSURES

Intermittent lane reductions are scheduled on northbound and southbound 15, between Weirick Rd. and State Route 60, weeknights. During lane reductions, at least one lane will remain open at all times.

The closure schedule is as follows:

Date, Time Location Detour
Monday, Oct. 28
9 p.m. to 6 a.m.
Cantu-Galleano Ranch Rd. Southbound 15 on-ramp

Weirick Rd.
Northbound 15 off-ramp

Use Riverside Dr.

Use Cajalco Rd.

Tuesday, Oct. 29
9 p.m. to 6 a.m.
El Cerrito Rd.
Northbound 15 on-ramp
Southbound 15 on-ramp
Use Ontario Ave.
Wednesday, Oct. 30
9 p.m. to 6 a.m.
Cajalco Rd.
Northbound & southbound 15 on- and off-rampsMain St.
Eastbound 91 on-rampMagnolia Ave.
Northbound 15 on-ramp
Use El Cerrito Rd.

Use West 2nd St.

Use Ontario Ave.

Thursday, Oct. 31
9 p.m. to 6 a.m.
Magnolia Ave.
Northbound 15 on-ramp
Use Ontario Ave.
Friday, Nov. 1
10 p.m. to 6 a.m.
Magnolia Ave.
Northbound 15 on-rampHidden Valley Ave.
Northbound 15 on- and
off-ramp
Use Ontario Ave.

Use Second St.

 


CONNECTOR CLOSURES

Closures of the 15/91 connectors are also planned weeknights. Detours will be clearly marked.

The closure schedule is as follows:

Date, Time Location Detour
Monday, Oct. 28 – Friday, Nov. 1
9 p.m. to 7 a.m.
Eastbound 91 to northbound 15 connector Use Main St. to
Hidden Valley Pkwy.
Monday, Oct. 28,
Tuesday, Oct. 29 &
Friday, Nov. 1
9 p.m. to 7 a.m.
Westbound 91 to northbound 15 connector Use Main St.
Monday, Oct. 28 –
Wednesday, Oct. 30
9 p.m. to 7 a.m.
Southbound 15 to westbound 91 connector Use Magnolia Ave.
Wednesday, Oct. 31 –
Friday, Nov. 1
9 p.m. to 6 a.m.
Northbound 15 to westbound 91 connector

Northbound15 to eastbound 91 connector

Use Hidden Valley Pkwy.

VIDEO: 15 FACTS ON THE 15 EXPRESS

Check out our latest video in our series, 15 Facts on the 15 Express. See what the 15 Express team does to be environmental stewards in this environmentally sensitive area.


Neighboring Projects

60 Swarm Pavement Rehabilitation Project: :  Full closures of westbound State Route 60, between I-15 and the 60/91/215 interchange in Riverside, will occur through November. For more information, visit www.60swarm.com.

Cajalco Rd. / I-15 Interchange Improvement Project: For schedule and closure information, visit i15cajalco.com .

Limonite Ave / I-15 Interchange Improvement Project: For schedule and closure information, visit i15limonite.org .

Caltrans work on 15/91 Interchange: Beginning Monday, Oct. 28, Caltrans crews will be conducting several geotechnical tests along eastbound and westbound 91 between Serfas Club Dr. and the 15/91 Interchange. The testing will take place between 11 p.m. and 4 a.m. weeknights over the next four weeks and require one to two-lane closures in addition to adjacent ramp closures, such as Main St., Serfas Club Dr., and Lincoln Ave. At least one lane will remain open at all times.


Due to the dynamic nature of construction, this information is subject to change.

If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.

Print Friendly, PDF & Email