Construction Update – Week of Oct 21

I-15 RAMP & LANE CLOSURES

On Thursday, Oct. 24 beginning at 8:30 a.m., one lane will be available on El Cerrito Rd. / Foothill Pkwy. beneath the I-15; flaggers will be directing motorists.

Intermittent lane reductions are scheduled on northbound and southbound 15, between Weirick Rd. and State Route 60, weeknights. During lane reductions, at least one lane will remain open at all times.

The closure schedule is as follows:

Date, Time Location Detour
Monday, Oct. 21 – Friday, Oct. 25
9 p.m. to 7 a.m.
Eastbound 91 to northbound 15 connector Use Main St. to
Hidden Valley Pkwy.
Wednesday, Oct. 23
9 p.m. to 7 a.m.
Westbound 91 to northbound 15 connector

Southbound 15 to eastbound 91 connector

Use Main St.
Thursday. Oct. 24
9 p.m. to 7 a.m.
Southbound 15 to eastbound 91 connector

Southbound 15 to westbound 91 connector

Use Main St.

Use Magnolia Ave.

Friday, Oct. 25
9 p.m. to 6 a.m.
Southbound 15 to eastbound 91 connector

Southbound 15 to westbound 91 connector

Use Main St.

Use Magnolia Ave.

 


CONNECTOR CLOSURES

Closures of the 15/91 connectors are also planned weeknights. Detours will be clearly marked.

The closure schedule is as follows:

Date, Time Location Detour
Monday, Oct. 21 – Friday, Oct. 25
9 p.m. to 7 a.m.
Eastbound 91 to northbound 15 connector Use Main St. to
Hidden Valley Pkwy.
Wednesday, Oct. 23
9 p.m. to 7 a.m.
Westbound 91 to northbound 15 connector

Southbound 15 to eastbound 91 connector

Use Main St.
Thursday. Oct. 24
9 p.m. to 7 a.m.
Southbound 15 to eastbound 91 connector

Southbound 15 to westbound 91 connector

Use Main St.

Use Magnolia Ave.

Friday, Oct. 25
9 p.m. to 6 a.m.
Southbound 15 to eastbound 91 connector

Southbound 15 to westbound 91 connector

Use Main St.

Use Magnolia Ave.


55 MPH IN CONSTRUCTION ZONE

Please drive slowly and carefully in the 15 Express Lanes construction project area for your safety and the safety of our construction workers. The speed limit is 55 miles per hour for the full project limits. Traffic fines are doubled in a construction zone.


VIDEO: CONSTRUCTION RECAP

See what crews accomplished last month on the 15 Express Lanes project in our latest construction recap video.


Neighboring Projects

60 Swarm Pavement Rehabilitation Project: :  Full closures of westbound State Route 60, between I-15 and the 60/91/215 interchange in Riverside, will occur through November. For more information, visit www.60swarm.com.

Cajalco Rd. / I-15 Interchange Improvement Project: For schedule and closure information, visit i15cajalco.com .

Limonite Ave / I-15 Interchange Improvement Project: For schedule and closure information, visit i15limonite.org .


Due to the dynamic nature of construction, this information is subject to change.