Construction Update – Week of Nov 18

THIS WEEKEND!  I-15 NIGHTTIME FULL CLOSURE – SATURDAY, NOV. 16

A nighttime full closure of northbound I-15 from Magnolia Ave. to the 91, including the I-15 northbound and southbound Express Lanes, is scheduled on Saturday night, Nov. 16, from midnight to 5 a.m. for overhead sign work. The Magnolia Ave. northbound 15 on-ramp also will be closed. Motorists should use McKinley St. or Main St. to access northbound 15. Please expect delays and plan accordingly.

 


I-15 RAMP & LANE CLOSURES

Intermittent weeknight lane reductions are scheduled on northbound and southbound 15, between Weirick Rd. and State Route 60. During lane reductions, at least one lane will remain open at all times.

There also will be street flagging on Riverside Ave. intermittently, Monday through Friday, between 8 a.m. and 2 p.m.

The closure schedule is as follows:

Date, Time Location Detour
Monday, Nov. 18 –
Wednesday, Nov. 20
9 p.m. to 6 a.m.
Hidden Valley Pkwy. Northbound 15 on-ramp

Magnolia Ave.
Northbound 15 on-ramp

Use Second St.

Use Ontario Ave.

Thursday, Nov. 21
9 p.m. to 5 a.m.
Hidden Valley Pkwy. Northbound 15 on-ramp

Magnolia Ave.
Northbound 15 on-ramp
Southbound 15 off-ramp

Sixth St.
Northbound 15 off-ramp

Use Second St.

Use Ontario Ave.

Use Limonite Ave.

Friday, Nov. 22
9 p.m. to 6 a.m.
Hidden Valley Pkwy. Northbound 15 on-ramp
Southbound 15 off-rampMagnolia Ave.
Northbound 15 on-ramp
Southbound 15 off-ramp
Use Second St.

Use Ontario Ave.

 


CONNECTOR CLOSURES

Closures of the 15/91 connectors are also planned weeknights from 9 p.m. to 5 a.m. Motorists should use arterial roadways when possible; detours will be clearly marked.

The following connectors may be closed intermittently on weeknights:

  • Westbound 91 to northbound 15 connector
  • Westbound 91 to southbound 15 connector
  • Eastbound 91 to northbound 15 connector
  • Eastbound 91 to southbound 15 connector
  • Northbound 15 to westbound 91 connector
  • Northbound 15 to eastbound 91 connector
  • Southbound 15 to westbound 91 connector

 


VIDEO: CONSTRUCTION RECAP

Check out the latest news on the 15 Express Lanes Project in our construction recap video for October.


Neighboring Projects

60 Swarm Pavement Rehabilitation Project: : The weekend of Nov. 15-18 will be the final closures of westbound State Route 60, between I-15 and the 60/91/215 interchange in Riverside. For more information, visit www.60swarm.com.

Cajalco Rd. / I-15 Interchange Improvement Project: For schedule and closure information, visit i15cajalco.com .

Limonite Ave / I-15 Interchange Improvement Project: The project is nearing completion and is open for use. The ribbon cutting ceremony was held Nov. 14 to commemorate the opening of the new Limonite Ave. interchange.

Caltrans work on 15/91 Interchange: Caltrans crews are conducting several geotechnical tests along eastbound and westbound 91 between Serfas Club Dr. and the 15/91 Interchange. The testing will take place 11 p.m. to 4 a.m. weeknights through the end of November and may require one to two-lane closures and adjacent ramp closures, such as Main St., Lincoln Ave., and Serfas Club Dr. At least one lane will remain open at all times.


Due to the dynamic nature of construction, this information is subject to change.