Construction Update – Week of May 25

In observance of Memorial Day, no closures are scheduled from Friday, May 22, through Monday, May 25.

We hope you enjoy the holiday weekend and please drive safely!


I-15 LANE, RAMP & CONNECTOR CLOSURES

Crews are working extended hours due to fewer cars on the road. Daytime (8 a.m. to 3 p.m.) or nighttime (8 p.m. to 5 a.m.) lane reductions may be needed on northbound and southbound 15, between Weirick Rd. and Route 60. During lane reductions, at least one lane will remain open at all times.

Intermittent nighttime closures on the 15/91 and 15/60 connectors are also planned.

Date, Time Location
Monday, May 25 No closures scheduled due to Memorial Day
Tuesday, May 26
8 p.m. to 5 a.m.

*9 p.m. to 5 a.m.

15/60 Connectors
15 northbound to 60 east/west
*60 east/west to 15 southbound

15/91 Connectors
*91 eastbound to 15 northbound
*15 southbound to 91 east/west

Northbound 15
Cantu-Galleano Ranch Rd. on-ramp
*Hidden Valley Pkwy. on-ramp

Southbound 15
*Second St. on-ramp

Wednesday, May 27
9 p.m. to 5 a.m.
15/91 Connectors
91 eastbound to 15 northbound

Northbound 15
Hidden Valley Pkwy. on- & off-ramps
Cajalco Rd. on- & off-ramps
El Cerrito Rd. on- & off-ramps
Ontario Ave. off-ramp

Thursday, May 28
8 p.m. to 5 a.m.

*9 p.m. to 5 a.m.

15/91 Connectors
15 northbound to 91 east/west

Northbound 15
Magnolia Ave. on-ramp
*Hidden Valley Pkwy. on-ramp

Southbound 15
*Cajalco Rd. on- & off-ramps
*El Cerrito Rd. on- & off-ramps
*Ontario Ave. on- & off-ramps

Friday, May 22
9 p.m. to 6 a.m.

*10 p.m. to 7 a.m.

15/91 Connectors
91 eastbound to 15 southbound
*15 southbound to 91 eastbound
*91 westbound to 15 southbound

Northbound 15
Hidden Valley Pkwy. on-ramp

Southbound 15
*Magnolia Ave. off-ramp

Eastbound 91
*Main St. on-ramp


PAVEMENT GRINDING ON I-15: EXPECT NOISE  DURING DAYTIME & NIGHTTIME 

Pavement grinding on I-15, between Magnolia Ave. and State Route 60, is scheduled during the weekdays and weeknights. The grinding of existing and temporary lanes are necessary for operational and safety reasons, as well as future noise reduction of motorists using the I-15 and 15 Express Lanes.

This activity will create noise, due to equipment movement, back-up alarms, and related construction activity. We apologize for any inconvenience this may cause.


UPCOMING: NIGHTTIME FULL CLOSURES ON I-15

A full closure of the northbound 15 at Magnolia Ave. including the 15 Express Lane connectors, is tentatively scheduled June 1,2, and 3, from 10 p.m. to 4 a.m.

A full closure of southbound 15 at Hidden Valley Pkwy. is tentatively scheudled June 4, 5, and 8, from 11 p.m to 5 a.m.

More information, including detours, will be provided next week.

 


Due to the dynamic nature of construction, this information is subject to change.

If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.