Construction Update – Week of Mar. 11

NIGHTTIME LANE & RAMP CLOSURES

Intermittent lane reductions are scheduled on northbound and southbound I-15, between Weirick Rd. and SR-60, from 8 p.m. to 5 a.m. weeknights and up to 7 a.m. weekend mornings. During lane reductions, at least one lane will remain open at all times.

 


LANE REDUCTIONS ON EL CERRITO RD.

Crews will be reducing lanes on El Cerrito Rd. nightly from Monday, March 11 to Friday, March 15 from 8 p.m. to 5 a.m. for drilling work. At least one lane will remain open in each direction.

A new, temporary traffic configuration is in place on El Cerrito Road at I-15 to allow crews to widen the bridge. Please allow for extra travel time and use caution when traveling through the area.

 


DAYTIME FLAGGING ON CORONA AVE.

Daytime flagging operations will continue weekdays for bridge widening work on Corona Ave. at I-15 through March.


Neighboring Projects

Cajalco Rd. / I-15 Interchange Improvement Project: Lane reductions are expected at Cajalco Ave. over the next several weeks. Visit i15cajalco.com for more information.

Limonite Ave / I-15 Interchange Improvement Project: Full freeway closures are expected on the 15 at Limonite Ave. over the next few weeks. Visit i15limonite.org for dates and more information.

Caltrans Maintenance: Caltrans crews will be closing the northbound 15 to the westbound 91 connector and the Main St. off-ramp in Corona for survey work on Saturday, March 9 from 5 a.m. to 10 a.m. Please reduce your speed in the work zone. For more information, visit the Caltrans website.


Due to the dynamic nature of construction, this information is subject to change.

If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.

Print Friendly, PDF & Email