I-15 LANE, RAMP & CONNECTOR CLOSURES
Daytime (9 a.m. to 3 p.m.) or nighttime (8 p.m. to 5 a.m.) lane reductions may be needed on northbound and southbound 15, between Weirick Rd. and Route 60. During lane reductions, at least one lane will remain open at all times.
Intermittent nighttime closures on the 15/91 connectors are also planned.
The closure schedule is as follows:
Date, Time | Location |
Monday, June 29 8 p.m. to 4 a.m. *9 p.m. to 5 a.m. **9 p.m. to 6 a.m. |
15/91 Connectors 91 east/west to 15 north *15 south to 91 east Eastbound 91 |
Tuesday, June 30 9 p.m. to 5 a.m. |
15/91 Connectors *15 south to 91 east |
Wednesday, July 1 9 p.m. to 5 a.m. |
15/91 Connectors 91 east/west to 15 south Southbound 15 |
NIGHTTIME FULL CLOSURES OF EL CERRITO RD. AT I-15 BRIDGE
Full closures of El Cerrito Rd. at I-15 are scheduled weeknights, from 7:30 p.m. to 5 a.m., through mid-July. Crews are retrofitting existing bridge columns at I-15 for earthquake safety.
PAVEMENT GRINDING ON I-15; EXPECT DAYTIME & NIGHTTIME NOISE
Pavement grinding on I-15 continues weekdays and weeknights through July. Crews will grind existing and temporary lanes within the project area to enhance safety and operations. Please pardon our noise while crews create a smoother, safer and quieter ride.
TEMPORARY LANE REDUCTION ON EASTBOUND 91 TO SOUTHBOUND 15 CONNECTOR
The eastbound 91 to southbound 15 connector is reduced to one lane to allow crews to safely complete bridge work. The lane reduction will be in place until approximately mid-July. We apologize for the additional travel time this is causing for motorists.
PROJECT MILESTONE: MAJOR PAVING COMPLETED FOR NEW EXPRESS LANES
With major concrete paving work complete, crews dismantled the batch plant along northbound 15 at Hidden Valley Pkwy. this week.
During the past two years, the batch plant mixed 110,000 cubic yards of concrete – enough to cover 155 football fields with a 4-inch concrete slab!
An overhead conveyor belt delivered the concrete directly to the I-15 median, reducing truck trips on roadways and minimizing effects on motorists.

Batch plant in full operation

With major paving completed, crews are dismantling the batch plant