Construction Update – Week of July 15

NIGHTTIME RAMP, CONNECTOR CLOSURES

Intermittent lane reductions are scheduled on northbound and southbound 15, between Weirick Rd. and State Route 60, from 8 p.m. to 5 a.m., weeknights. During lane reductions, at least one lane will remain open at all times.

The eastbound 91 to southbound 15 Express Lanes Connector and #1 General Purpose Lane are scheduled to be closed Monday, July 15 from 10 p.m. to 4 a.m.

The following closures are also scheduled:

Date, Time Location
Monday, July 15
9 p.m. to 5 a.m.
Eastbound 91 to Northbound 15 Connector

Northbound 15 Magnolia Ave.
On-ramp

Tuesday, July 16
9 p.m. to 5 a.m.
Eastbound 91 to Northbound 15/ Southbound 15 Connectors

Westbound 91 to Southbound 15 Connector

Wednesday, July 17
9 p.m. to 5 a.m.
Eastbound 91 to Northbound 15 Connector
Thursday, July 18
9 p.m. to 5 a.m.
Eastbound & Westbound 91 to Southbound 15 Connectors

Northbound 15 Magnolia Ave. On-ramp


WHAT IS THAT?

This conveyor belt spans the northbound lanes of I-15 near Hidden Valley Parkway in Norco. The conveyor belt was built to carry concrete from the batch plant, over the roadway, to waiting trucks, which then carry to the concrete to the paving machine. This overhead transfer system eliminates the need for concrete-carrying trucks to cross I-15, requires fewer trucks to supply the paving machine with material, and speeds up the paving process for the 15 Express Lanes Project.


6th STREET CLOSURE IN CORONA

Crews will be placing girders and closing 6th Street at I-15 on Thursday, July 18, from 7 p.m. to 6 a.m. There will be nightly lane reductions from 8 p.m. to 5 a.m. weeknights for demolition work.


NEIGHBORING PROJECT: 91 EXPRESS LANES CLOSURES

The 91 Express Lanes will be closed intermittently from Friday night, July 12 to Tuesday morning, July 16 for toll system upgrades. A complete closure schedule is listed below:


Neighboring Projects

Cajalco Rd. / I-15 Interchange Improvement Project: Alternating freeway lane and ramp closures are scheduled. Visit i15cajalco.com for closure information.

Limonite Ave / I-15 Interchange Improvement Project:Ramp and street closures will take place in mid-July. Visit i15limonite.org for closure information.


Due to the dynamic nature of construction, this information is subject to change.

If information is needed in another language, please contact RCTC at (951) 787-7141 for free translation services.