15 FACTS ON THE 15 EXPRESS LANES:
Innovations in Bridge Building
Check out the latest video in our 15 Facts on the 15 Express Lanes series, focusing on innovations in bridge building on the project.
FULL NIGHTTIME CONNECTOR CLOSURES
Crews will be closing the 15/91 connectors nightly for construction work from Monday, Jan. 14 to Thursday, Jan. 17.
Schedule | Closure Location |
Monday, Jan. 14 9 p.m to 5 a.m. |
|
Tuesday, Jan. 15 – Thursday, Jan. 17 9 p.m. to 5 a.m. |
|
Detours will be clearly marked. View the map below for schedule and detours.
DAYTIME FLAGGING ON CORONA AVE.
Daytime flagging operations will be in place on Corona Ave. at I-15, near Parkridge Ave., for bridge widening work, beginning Monday, Jan. 28, from 6 a.m. to 2 p.m. Flaggers will be directing motorists through the area for several weeks.
NIGHTTIME LANE CLOSURE SCHEDULE
Intermittent lane reductions may occur on northbound and southbound I-15 from 8 p.m. to 5 a.m. weeknights and up to 7 a.m. weekend mornings. At least one lane will remain open at all times.