Construction Update – Week of Apr 20

15 FACTS ON THE 15 EXPRESS LANES: COVID-19 SAFE JOB PRACTICES

Check out the latest video in our “15 Facts on the 15 Express Lanes” series. Learn how our project teams and crews are following safe worksite standards during this unprecedented time of COVID-19.

 


I-15 LANE, RAMP & CONNECTOR CLOSURES

With fewer cars on the roads, crews are working extended hours. Daytime (9 a.m. to 3 p.m.) or nighttime (8 p.m. to 5 a.m.) lane reductions may be needed on northbound and southbound 15, between Weirick Rd. and Route 60. During lane reductions, at least one lane will remain open at all times.

Intermittent nighttime closures on the 15/91 connectors and 15/60 connectors are also scheduled.

The closure schedule is as follows:

Date, Time Location
Monday, April  20

8 p.m. to 5 a.m.

 

 

*9 p.m. to 5 a.m.

15/91 Connectors
15 southbound to 91 eastbound

15/60 Connectors
15 northbound to 60 eastbound
*15 northbound to 60 westbound

Southbound 15
*Second St. on-ramp
*Hidden Valley Pkwy. off-ramp

Tuesday, April 21
9 p.m. to 5 a.m.
15/91 Connectors
15 southbound to 91 eastbound
15 southbound to 91 westbound

Southbound 15
Hidden Valley Pkwy. on- & off-ramps

Wednesday, April 22
8 p.m. to 5 a.m.

*9 p.m. to 5 a.m.

Northbound 15
Second St. on-ramp

15/91 Connectors
*91 westbound to 15 southbound
*91 westbound to 15 northbound

Southbound 15
*Second St. on-ramp

Thursday, April 23
8 p.m. to 5 a.m.

*9 p.m. to 5 a..m.

Northbound 15
Hidden Valley Pkwy. on- & off-ramps
Second St. on-ramp

15/91 Connectors
*91 westbound to 15 southbound

Friday, April 24
9 p.m. to 7 a.m.

*10 p.m. to 6 a.m.

Northbound 15
Hidden Valley Pkwy. on- & off-ramps
Second St. on-ramp
*Magnolia Ave. on-ramp

15/91 Connectors
*15 southbound to 91 eastbound
*15 southbound to 91 westbound

Saturday, April 25
11 p.m. to 7 a.m.
15/91 Connectors
15 northbound to 91 eastbound
15 northbound to 91 westbound

Northbound 15
Magnolia Ave. on-ramp

Please note, closures may change due to inclement weather. 


15 EXPRESS LANE CLOSURES

The northbound 15 connector to the westbound 91 Express Lanes will be closed nightly, Monday, April 20 through Friday, April 24, from 8 p.m. to 5 a.m.

The eastbound 91 Express Lanes connector to the southbound 15 will be closed  nightly, Monday, April 20 through Wednesday, April 22, from 9 p.m. to 5 a.m.


NIGHTTIME LANE CLOSURES ON 91; CLOSURE OF MAIN ST. ON-RAMP TO EASTBOUND 91

Intermittent lane closures are scheduled on the eastbound 91 (9 p.m. to 5 a.m.) and westbound 91 (8 p.m. to 4 a.m.), between McKinley St. and Main St., nightly, Monday, April  20 through Thursday, April 23.

The Main St. on-ramp to eastbound 91 will also be closed nightly, Monday, April 20 through Wednesday, April 22, (9 p.m. to 6 a.m) to re-stripe lanes.

 


Due to the dynamic nature of construction, this information is subject to change.