I-15/LIMONITE INTERCHANGE
15 Express Lanes crews are on target to complete paving work in the Limonite Interchange area by the end of this month. The County of Riverside is then scheduled to begin work on the I-15/Limonite Avenue Interchange Project by the end of Sept. 2018. For more information about this project, visit the County of Riverside’s website.
LANE & RAMP CLOSURES
There will be weeknight lane closures throughout the project area on northbound and southbound I-15 between SR-91 and SR-60. Crews will be working between 8 p.m. and 5 a.m. nightly for paving, striping, setting k-rail and grinding.
At least one lane in each direction will remain open at all times.
Scheduled ramp closures include:
Schedule | Location |
Tuesday, Aug. 7 8 p.m. to 5 a.m. |
– Northbound I-15: Hidden Valley Pkwy off-ramp – Northbound I-15: Second St. off- ramp |
Wednesday & Thursday, Aug. 8 -9 8 p.m. to 5 a.m. nightly |
– Northbound I-15: Sixth St. off- and on-ramps |
Neighboring Project
Cajalco Road / I-15 Interchange Improvement Project: Road work and closures may occur within the I-15 corridor as part of the City of Corona’s Cajalco Road / I-15 Interchange Improvement Project. Click to view construction updates for this neighboring project or for more information, visit the project’s website at www.i15cajalco.com.